Table of Contents

Communicate time ranges or scope ranges

The Iron Triangle of Project Management represents the three key constraints, scope, time, and costs, that must be carefully balanced in any project.

You should be able to communicate based on time and on scope.

In order to answer these questions you will need two things. The backlog and the velocity chart.

Example Backlog

We have a backlog with the following user stories.

Product backlog item / User story Effort estimation
Story 1 3
Story 2 1
Story 3 13
Story 4 8
Story 5 5
Story 6 5
Story 7 3
Story 8 8
Story 9 3
Story 10 13

Example Velocity Chart

The projects velocity chart looks like this:

Velocity Chart

Answering when a specific set of stories is finished

If we want to estimate when story 6 will be finished, we can use the following calculations:

We finish our work at the end of each sprint, so we round up the estimated remaining sprints.

Answer: We expect it will take between 3 and 5 sprints to finish up until story 6.

Answering what stories are finished at a specific date

If we want to estimate what we can deliver in two months, we can use the following calculations:

Answer: We expect to be able to deliver up until story 5, maybe some of the stories up until story 9, and we will definitely not deliver story 10.

References

© 2024 Rob van der Velden. All rights reserved.